Church Roof Repair Project progress report #4

The full gang set about completing the stripping of slates and old battens on Monday, 7 February. They then covered the nave roof with new Wondervent underlay.

Another bag of redundant tiles and battens is winched down from the nave roof

 

New underfelt covering nave roof seen from the top of the tower.

On Tuesday new battens were nailed from ridge to gutter of the chancel roof and new planks screwed horizontally across them to make the boarding strong enough to withstand the force of up-draughts created by strong winds acting on the future stainless steel covering. By the end of the day the extra boarding was complete and covered with underfelt. A start was made in the drizzle on Wednesday to investigate the lead lined gutter behind the chancel parapets.

What looks like new multi-strip lighting in the chancel ceiling is actually the sky on a dry 8 February – a sight that we hope will not present itself again for a century or two!

 

Harry nails the extra layer of planks to the north side of the chancel roof.

 

Jo adding the last planks to the over-boarding of the chancel roof.

The timber for the batten roll joints required for the stainless steel sheeting were delivered and the heap of redundant old slates, felting and slate battens were taken away by Brad.

Removing the old slates and battens from site.